Exeter Substation Design-Build Project

E. P. Breaux Electrical, INC. (EPBI) of New Iberia, Louisiana (see http://epbreaux.com/), subcontracted Dorazio Enterprises, INC. (DEI) to complete all the civil sitework at the CPS Energy (see http://cpsenergy.com/Developers_Builders/New_Infrastructure/) Exeter Substation, San Antonio, Texas.

The Scope of Work consisted of: implementing and maintaining the Storm Water Pollution Prevention Plan (SW3P); site demolition; relocating underground utilities (water main, sanitary sewer and storm drain); installing a cast-in-place retaining wall, oil-containment pit, transformer pads and various other foundations; installing a pre-cast screen wall and metal access gate; and completing all sitework (excavation, base, grading for drainage, asphalt, curbing, striping, bollards, landscaping, etc.). Additional work occurred as a result of converting the overhead cable plans to an underground transmission cable system.